ANNEX 13
SUMMARY OF BUDGETS AND ANNEXES
Annex Description |
2021/22 £K |
||
Performance Review of maintenance capital delivery 20/21 |
9,027
|
||
Review of the City of York Council 2020/21 Capital Highways Programme |
Annual programme performance completion |
||
Carriageway resurfacing |
Completed |
% |
|
Acomb Road |
Completed |
|
|
Haxby Road |
Completed |
|
|
Huntington Road |
Completed |
|
|
James Street |
Completed |
|
|
Gale Lane |
Completed |
|
|
Hallcroft Lane |
Completed |
|
|
Bishopthorpe Road |
Deferred to 2022/23 |
EA Flood Defence works in the area |
|
Bad Bargain Lane |
Completed |
|
|
Hillcrest Gardens |
Completed |
|
|
Nunnery Lane |
Completed |
|
|
Tadcaster Road |
Completed |
91% completion Annual resurfacing programme |
|
Footway |
Completed |
% |
|
Monkgate Ph1 |
Completed |
|
|
Burton Stone Lane |
Deferred to17/05/2021 |
Funds diverted for emergency pothole repairs |
|
East Mount Road |
Completed |
|
|
The Village – Stockton |
Completed |
|
|
Haughton Road |
Completed |
|
|
Ostman Road |
Completed |
|
|
Hull Road |
Completed |
|
|
Rawcliffe Drive |
Completed |
|
|
A59 |
Completed |
|
|
Croft Court |
Completed |
|
|
Fulfordgate |
Completed |
|
|
Melbourne Street |
Deferred to24/05/2021 |
Funds diverted for emergency pothole repairs |
|
Hambleton Ave/Heatherbank |
Completed |
|
|
Fordlands Road |
Completed |
86% completion annual footway programme |
|
Pre-patching and Surface Dressing |
Completed |
% |
|
Moor Lane |
Completed |
|
|
A1237 |
Completed |
|
|
Wigginton Road |
Completed |
|
|
Preliminaries |
Completed |
100% completion annual surface dressing programme |
|
Large Patching |
Completed |
% |
|
Clarence Street |
Completed |
|
|
Tang Hall Lane |
Completed |
|
|
Vicarage Lane |
Completed |
|
|
St Helens Road |
Completed |
|
|
Main Street Wheldrake |
Completed |
|
|
Wheldrake Lane |
Completed |
|
|
Melrosegate |
Completed |
|
|
St Johns Street |
Completed |
|
|
Hull Road (Lilac Ave Jct) |
Completed |
|
|
Hamilton Drive East |
Completed |
|
|
Hull Road Dunnington |
Completed |
|
|
Huntington Road |
Completed |
|
|
Bootham Terrace |
Completed |
|
|
Askham Lane |
Completed |
|
|
Kent Street |
Mon 23rd Aug - Fri 27th Aug |
Need to carry out drainage works due to existing drainage being non-exist |
|
Elmfield Avenue |
Completed |
93% completion annual large patching programme |
|
Micro Patching |
Completed |
% |
|
Lowick |
19-04-21 & 20-04-21 |
Contractor not available until April 2021 |
|
Troutbeck |
19-04-21 & 20-04-21 |
Contractor not available until April 2021 |
|
Woodthorpe School Entrance |
24-04-21 only |
Contractor not available until April 2021 |
|
Overdale |
20-04-21 & 21-04-21 |
Contractor not available until April 2021 |
|
Glenridding |
20-04-21 to 22-04-21 |
Contractor not available until April 2021 |
|
Windermere |
21-04-21 & 22-04-21 |
Contractor not available until April 2021 |
|
Brambledene |
21-04-21 to 24-04-21 |
Contractor not available until April 2021 |
|
Dringfield Close |
26-04-21 & 27-04-21 |
Contractor not available until April 2021 |
|
Wains Road |
26-04-21 to 29-04-21 |
Contractor not available until April 2021 |
|
Lockwood Street |
19-04-21 to 26-04-21 |
Contractor not available until April 2021 |
|
|
|
0% completion annual micro patching programme |